New Plymouth District Council
PrintSiteMapContact

Maintenance

You are here > Home > A-Z of Council Services > Roads > Maintenance > Maintenance
  • Home
  • A-Z of Council Services
  • The Council & its People
  • Council Documents
  • Living in New Plymouth
  • Have Your Say
  • Visiting New Plymouth
Last Updated: 1/12/2008
- Bookmark this Page
- Rate this Page
- Report an Error

Search

Maintenance

A contractor resealing a road in New Plymouth. Footpath cracked and unsafe? Road sign damaged? Pot holes?

If you notice something to do with the roads or footpaths that needs maintenance please let us know. This includes:

  • Broken or flickering street lights.
  • Loose seal which may cause damage to vehicles or an accident.
  • Faulty traffic lights.
  • Faded road markings.
  • Broken glass or debris on the road.
  • Overhanging branches blocking footpaths.
  • Contact us form

We are responsible for the maintenance of local roads. This includes streetlights, cycle lanes / cycle ways, footpaths, seating and other street furniture, pedestrian crossings and ramps, road signs, road markings, repair and maintenance of existing kerb and channel, street cleaning, traffic signals, service covers (e.g. manhole covers, grates) and maintaining vegetation on road sides.

The clean up of spillages such as diesel on local roads, crash response and debris cleanup is also done by us.

Vegetation maintenance

To eradicate any pest plants and hinder vegetation growth to ensure safe sight distances, we use chemical sprays on road sides and a non-toxic and non-chemical spray (usually Round-Up) in road side drains and inlets of culvert pipes.
 
Residents can ask for their property frontage to be a 'no spray zone', providing you manage the vegetation growth and pest plants at your own cost. The council will work with you to ensure the maintenance meets safety requirements.

  • No spray zone application form (Two pages 53KB PDF)
     

Road Works

This section is updated monthly.
Last update: 1 December 2008
Next update: 12 January 2009

You can sort the information in the tables below by work, location, contractor, start date and finish by clicking on each heading. For more information about roading projects please contact us on 06-759 6060 or use our contact us form.

  • Contact us

Return to top

Projects under way

Work Location Contractor Start date Finish date
CBD camera maintenance New Plymouth, Waitara and Inglewood CBDs Obertech Security
20/10/2005 26/01/2009
Road markings District wide Independent Road Markers 2006 26/06/2009
Traffic signal maintenance District wide including state highways
Wells Instrument and Electrical Ltd 2006 30/06/2009
Urban road general maintenance All townships Inframax Construction 2006 30/06/2009
Rural road general maintenance All rural areas
Fulton Hogan 01/07/2006 30/09/2011
CBD cleaning
New Plymouth, Waitara and Inglewood CBDs Chemwash Taranaki Ltd 2008
2010
Carrington Rd replacement of existing culvert #49
Carrington Rd (road position = 15.5km)  Taranaki Civil Construction Ltd
14/04/2008 27/02/2009 (on hold due to TRC requirements)
Carrington Rd bridge replacement
Carrington Rd (road position = 22.5km) Whitaker Civil Engineering 08/09/2008 30/1/2009
(completion
date extended
due to storm damage)
Everett Rd seal widening
Clark Rd to Manganui Rd Burgess & Crowley Civil Ltd 1/11/2008 1/02/2009
Urban road resealing Urban roads Ireland Roading Ltd 10/11/2008 28/02/2008
Dawson St Retaining Wall Renewal of existing wall Street and Cook 28/10/2008 28/11/2008
Kent Rd seal widening and minor repairs (stage two) Intersection of Kent Rd and SH3 (for 1.5km up Kent Rd)  Hurlstone Earthmoving Ltd 01/10/2008 20/02/2009
Mangaonga Rd replacement of existing culvert Mangaonga Rd (road position = 15.8km)  Hurlstone Earthmoving Ltd 01/11/2008 19/12/2008
Waitaanga Rd replacement of existing culvert Waitaanga Rd (road position = 9.7km)  Inframax 01/11/2008 19/12/2008
Brookes Tce kerb and channel replacement Brookes Tce Downer EDI Works Ltd 22/09/2008 23/01/2009
Queen St kerb and channel and footpath upgrade Queen St, Waitara Burgess & Crowley Civil Ltd 10/11/2008 28/02/2009
Mangorei Rd drainage and pavement upgrade (stage three) From Karaka St to Union St Taranaki Civil Engineering 1/11/2008 19/12/2008
Footpath slurry sealing New Plymouth Downer EDI Works Ltd Mid November 28/02/2009

Return to top

 

Projects coming up

Work Location Contractor Start date Finish date
Waitara Rd seal treatment Waitara Rd To be confirmed
Frankley Rd kerb, channel and footpath (stage two)
Leslie St kerb and channel and footpath upgrade Leslie St, Waitara To be confirmed

 

Recently completed road works

Work Location Contractor Start date Finish date
Frankley Rd kerb and channel (stage one) Frankley Rd from Barclay Close to Tukapa St (for 400m) Taranaki Civil Construction Ltd 01/06/2008 30/10/2008
Mohakatino Rd underslip repairs Mohakatino Rd Downer EDI Works Ltd 28/04/2008 26/10/2008
Carrington Rd Underslip Repairs Carrington Rd Whitaker Engineering 03/06/2008 26/10/2008

 

Related links

  • State highway maintenance responsibilities

Return to top

Subscribe to RSS feeds: http://www.newplymouthnz.com/RSS/Maintenance.xml
 

Contact Us

Address Icon. New Plymouth District Council, Civic Centre, Liardet St Postal Icon. Private Bag 2025 New Plymouth New Zealand 4342
Phone Icon. 06-759 6060 Fax Icon. 06-759 6072 Email Icon.  Email Contact Us Icon.  Contact Us Form Disclaimer Icon.  Terms and Conditions RSS feed icon.  Find out more about RSS
  • Home
  • A-Z of Council Services
  • The Council & its People
  • Council Documents
  • Living in New Plymouth
  • Have Your Say
  • Visiting New Plymouth