Maintenance

A contractor resealing a road in New Plymouth. Footpath cracked and unsafe? Road sign damaged? Pot holes?

If you notice something to do with the roads or footpaths that needs maintenance please let us know. This includes:

  • Broken or flickering street lights.
  • Loose seal which may cause damage to vehicles or an accident.
  • Faulty traffic lights.
  • Faded road markings.
  • Broken glass or debris on the road.
  • Overhanging branches blocking footpaths.
  • Contact us form

We are responsible for the maintenance of local roads. This includes streetlights, cycle lanes / cycle ways, footpaths, seating and other street furniture, pedestrian crossings and ramps, road signs, road markings, repair and maintenance of existing kerb and channel, street cleaning, traffic signals, service covers (e.g. manhole covers, grates) and maintaining vegetation on road sides.

The clean up of spillages such as diesel on local roads, crash response and debris cleanup is also done by us.

Vegetation maintenance

To eradicate any pest plants and hinder vegetation growth to ensure safe sight distances, we use chemical sprays on road sides and a non-toxic and non-chemical spray (usually Round-Up) in road side drains and inlets of culvert pipes.
 
Residents can ask for their property frontage to be a 'no spray zone', providing you manage the vegetation growth and pest plants at your own cost. We will work with you to ensure the maintenance meets safety requirements. 

  • Contact us form

Road Works

This section is updated regularly.
Last update: 27 May 2009
Next update: 1 July 2009

You can sort the information in the tables below by work, location, contractor, start date and finish by clicking on each heading. For more information about roading projects please contact us on 06-759 6060 or use our contact us form.

  • Contact us

Return to top

Projects under way

Work Location Contractor Start date Finish date
CBD camera maintenance New Plymouth, Waitara and Inglewood CBDs Obertech Security
20/10/2005 30/11/2009
Road markings District wide Independent Road Markers 2006 30/06/2009
Traffic signal maintenance District wide including state highways
Wells Instrument and Electrical Ltd 2006 30/06/2009
Urban road general maintenance All townships Inframax Construction 2006 30/06/2009
Rural road general maintenance All rural areas
Fulton Hogan 01/10/2008  30/09/2011
CBD cleaning
New Plymouth, Waitara and Inglewood CBDs Chemwash Taranaki Ltd 2008
2010
Carrington Road replacement of existing culvert #49
Carrington Road (road position = 15.5km)  Taranaki Civil Construction Ltd
14/04/2008 31/03/2010
Pre-loading of embankment. Work to begin summer 09/10.
Kent Road seal widening and minor repairs (stage two) Intersection of Kent Road and SH3 (for 1.5km up Kent Road) + extra 300m Hurlstone Earthmoving Ltd 09/02/2009 31/05/2009
Queen Street kerb and channel and footpath upgrade Queen Street, Waitara Burgess & Crowley Civil Ltd 25/05/2009 04/08/2009
Waikaramarama Road bridge renewal Waikaramarama Road, Uruti Taranaki Civil Construction 30/03/2009 30/06/2009
Rural pre-reseal repairs and reseal Rural areas Fulton Hogan Mid February 30/06/2010
Egmont Road underslip repairs Egmont Road Whitaker Civil Engineering Mid April 31/05/2009
Okau, Kaipikari and Kaka roads underslip repairds Okau, Kaipikari and Kaka roads Keenan Contractors 23/03/2009 31/05/2009
Mahoetahi Road seal widening Mahoetahi Road Whitaker Civil Engineering Late April 31/05/2009
Frankley / Brois roundabout Frankley Road and Brois Street intersection Whitaker Civil Construction 01/05/2009 30/06/2009
Maikaikatea Road safety realignment and sealing Maikaikatea Road Fulton Hogan 01/05/2009 30/06/2009
Minor concrete works (Kea crossings, central island etc) Donnely Street, Lemon Street, Belt Road, Junction Road, Mangorei Road Civilscape 01/05/2009 30/06/2009
Carrington Road retaining wall Carrington Road Taranaki Civil Construction 01/07/2009 31/07/2009

Return to top

 

Projects coming up

Work Location Contractor Start date Finish date
Waitara Rd seal treatment Waitara Rd from level crossing to Pennington Road To be confirmed Tenders have closed.
Frankley Rd kerb and channel and footpath upgrade (stage two) Frankley Rd To be confirmed
Seal treatments Various locations, district wide. To be confirmed
Karina Rd Extension New road and footpath To be confirmed Tender documents are being prepared.

 

Recently completed road works

Work Location Contractor Start date Finish date
Footpath slurry sealing   New Plymouth   Downer EDI Works Ltd   Mid November 30/04/2009
Ngatoto Road bridge replacement Ngatoto Road North, Uruti Concrete Structures Ltd 01/03/2009 30/06/2009

 

Related links

  • State highway maintenance responsibilities

Return to top

Subscribe to RSS feeds: http://www.newplymouthnz.com/RSS/Maintenance.xml
 

Contact Us

Address Icon. New Plymouth District Council, Civic Centre, Liardet St Postal Icon. Private Bag 2025 New Plymouth New Zealand 4342
Phone Icon. 06-759 6060 Fax Icon. 06-759 6072 Email Icon.  Email Contact Us Icon.  Contact Us Disclaimer Icon.  Terms & Conditions RSS feed icon.  About RSS Accessibility Accessibility
  • Home
  • A-Z of Council Services
  • The Council & its People
  • Council Documents
  • Living in New Plymouth
  • Have Your Say
  • Visiting New Plymouth